The Annual Work Schedule of 2016 has been changed (22 March)

Dear Partners,

The Annual Work Schedule of 2016 has been changed.

The Modified Planned tasks indicated on the published sheet have been modified respect the date and/or the Local Distribution Company concerned information.

The following changes have been made with regard to cross-border points:

  • (ID: FGSZ_E_HA_201601) the earlier published capacity reduction at Beregdaróc 800 (HU>UA) network point has been cancelled.
  • (ID: FGSZ_K_KA_2016_011) the period and extent of the earlier published capacity reduction at Mosonmagyaróvár (AT>HU) network point has been modified.

Work Schedule for the Hungarian Gas Transmission System Subject to 2016 is available on our website: Maintenance Plan.

Best Regards, 

FGSZ Ltd, TSO