RBP IP TP

The Annual Work Schedule for Hungarian Gas Transmission System of 2019 has been published

2019. 01. 15.

The Annual Work Schedule for Hungarian Gas Transmission System of 2019 has been published

Dear Partners,

The Annual Work Schedule of 2019 has been published.

Maintenance plan of domestic production and storages are also available on www.fgsz.hu

The missing DSO related data will be published when received.

For easier transparency, we list planned reductions on Interconnection points.

Technical capacity will be available in 50% 6:00 13.05.2019 – 18:00 17.05.2019 Mosonmagyaróvár (AT>HU) (KAMOSONM1IIN) Elementary Point.
Technical capacity will be available in 0% (full stop) 8:00 12.06.2019 – 8:00 14.06.2019 Csanádpalota (HU>RO) (KECSANAD1HHN) Elementary Point.
Technical capacity will be available in 0% (full stop) 8:00 12.06.2019 – 8:00 14.06.2019 Csanádpalota (RO>HU) (KECSANAD1IIN) Elementary Point.
Technical capacity will be available in 0% (full stop) 7:00 03.10.2019 – 15:00 03.10.2019 Vecsés 4 (MGT>FGSZ) (VEVECSES1IIN) Elementary Point.
Technical capacity will be available in 0% (full stop) 7:00 03.10.2019 – 15:00 03.10.2019 Vecsés 4 (FGSZ>MGT) (VEVECSES1HHN) Elementary Point.

Best Regards,

FGSZ Ltd., TSO