Statement of FGSZ Ltd.

2025. 01. 30.

We inform you that on January 29, 2025, a gas leak occurred on the Vác–Romhány DN 300 high-pressure pipeline near Keszeg.

The responsible technical manager classified the incident as an emergency.

The colleagues of FGSZ Zrt. secured the site, there is no immediate danger, and no personal injury occurred.

During the repair of the damage to the pipeline, from 02:00 on January 31 to 08:00 on February 1, the capacities of the high-pressure natural gas system will not be available, therefore service interruptions are expected in the settlements served by the transfer facilities of Rétság, Romhány, Érsekvadkert, and Balassagyarmat during this period.

The emergency does not affect gas trading at the Hungarian-Slovak natural gas system interconnection point.

The employees of FGSZ are continuously working on the repair of the pipeline damage, and we ask for your patience and kind understanding due to the service interruption.