The repair work on the DN400 pipeline section between Kistokaj and Vargahegy has been completed

2025. 11. 15.

The system operator’s team began work early Friday morning. After draining the pipeline and exposing the fault, they replaced the damaged section of the pipe.

The affected pipeline segment has been replaced, and following successful inspection and pressure testing, the distribution network could be refilled.

FGSZ Ltd. has launched an investigation into the causes of the pipeline damage.