The Annual Work Schedule for Hungarian Gas Transmission System of 2021 has been published

2021. 01. 15.

Dear Partners,

The Annual Work Schedule of 2021 has been published.
Maintenance plan of storages is also available on our website.

The missing DSO related data will be published when received.

For easier transparency, we list planned reductions on Interconnection points.

  • Technical capacity will be available in 0% 6:00 07.09.2021 – 6:00 09.09.2021 Balassagyarmat (SK>HU) (VEBALASS2IIN) Elementary Point.
  • Technical capacity will be available in 0% 6:00 07.09.2021 – 6:00 09.09.2021 Balassagyarmat (HU>SK) (VEBALASS2HHN) Elementary Point.
  • Technical capacity will be available in 0% 6:00 11.10.2021 – 6:00 14.10.2021 Mosonmagyaróvár (AT>HU) (KAMOSONM1IIN) Elementary Point.

The Gas Connect Austria makes maintenance work it own system from 6:00 on 11.10.2021 to 6:00 on 16.10.2021. Technical capacity will be available in 0% on the Austrian side of HAG.

The current tables are available on our website: Maintenance Plan, Outages

Best Regards,

FGSZ Ltd., TSO