The Annual Work Schedule for the Hungarian Gas Transmission System of 2024 has been published

2024. 01. 15.

Dear Partners,

The Annual Work Schedule of 2024 has been published. Maintenance plan of storages is also available on www.fgsz.hu.

The missing DSO related data will be published when received.

For better transparency, we list planned reductions on the Interconnection points.

  • 0% of the technical capacity will be available during 07:00 26.06.2024 – 07:00 26.06.2024 Kiskundorozsma (HU>RS) (KEKISKUD1HHN) Elementary Point.
  • 0% of the technical capacity will be available during 07:00 04.09.2024 – 16:00 05.09.2024 Balassagyarmat (HU>SK) (VEBALASS2HHN) Elementary Point.
  • 0% of the technical capacity will be available during 06:00 21.09.2024 – 17:00 26.09.2024Beregdaróc 1400 (UA>HU) (HABEREGD1IIN) Elementary Point.
  • 50% of the technical capacity will be available during 06:00 23.09.2024 – 17:00 27.09.2024 Mosonmagyaróvár (AT>HU) (KAMOSONM1IIN) Elementary Point.
  • 0% of the technical capacity will be available during 08:00 08.10.2024 – 14:00 08.10.2024 Drávaszerdahely (CR>HU) (GEDRAVAS1IIN) Elementary Point.
  • 0% of the technical capacity will be available during 08:00 08.10.2024 – 14:00 08.10.2024 Drávaszerdahely (HU>CR) (GEDRAVAS1HHN) Elementary Point.

  • The Gas Connect Austria makes maintenance work on its own system from 6:00 on 23.09.2024 to 15:00 on 27.09.2024. 0% of the technical capacity will be available on the Austrian side of HAG.
  • The Gas Connect Austria makes maintenance work on its own system from 7:00 on 12.11.2024 to 15:00 on 12.11.2024. 0% of the technical capacity will be available on the Austrian side of HAG.
  • The GASTRANS makes maintenance work on its own system from 8:00 on 04.06.2024 to 8:00 on 11.06.2024. 0% of the technical capacity will be available on the Serbian side of Kiskundorozsma 2 (RS>HU).

The actual sheets are available on our website: Planned Outages

Best Regards,

FGSZ Ltd., TSO