The Annual Work Schedule of 2025 from 23 January
2026. 01. 23.
Dear Partners,
The Annual Work Schedule of 2026 has been published.
The Modified Planned task indicated on the published sheet have been modified respect the Local Distribution Company concerned information.
For better transparency, we list planned reductions on the Interconnection points.
- 50% of the technical capacity will be available during 06:00 05.05.2026. – 18:00 06.05.2026. Csanádpalota (HU>RO) (KECSANAD1HHN) Elementary Point.
- 50% of the technical capacity will be available during 06:00 05.05.2026. – 18:00 06.05.2026. Csanádpalota (RO>HU) (KECSANAD1IIN) Elementary Point.
- 50% of the technical capacity will be available during 06:00 02.06.2026. – 06:00 07.06.2026. Mosonmagyaróvár (AT>HU) (KAMOSONM1IIN) Elementary Point.
- 50% of the technical capacity will be available during 06:00 05.06.2026. – 06:00 10.06.2026. Balassagyarmat (HU>SK) (VEBALASS2HHN) Elementary Point.
- 50% of the technical capacity will be available during 06:00 05.06.2026. – 06:00 10.06.2026. Beregdaróc 800 (HU>UA) (HABEREGD1HHN) Elementary Point.
- 0% of the technical capacity will be available during 06:00 07.06.2026. – 06:00 09.06.2026. Hajdúszoboszló ("FGT" ki) (HAHAJDUS1ONN) Elementary Point.
- 0% of the technical capacity will be available during 06:00 07.06.2026. – 06:00 09.06.2026. Kardoskút (FGT ki) (KEKARDOS1ONN) Elementary Point.
- 0% of the technical capacity will be available during 06:00 07.06.2026. – 06:00 09.06.2026. Pusztaederics (FGT ki) (GEPEDERI1NNN) Elementary Point.
- 0% of the technical capacity will be available during 06:00 07.06.2026. – 06:00 09.06.2026. Zsana (FGT ki) (KEZSANA01NNN) Elementary Point.
- 50% of the technical capacity will be available during 06:00 09.09.2026. – 06:00 12.09.2026. Kiskundorozsma 2 (RS>HU) (KEKISKUD2IIN) Elementary Point.
- 0% of the technical capacity will be available during 10:00 10.09.2026. – 14:00 10.09.2026. Drávaszerdahely (CR>HU) (GEDRAVAS1IIN) Elementary Point.
- 0% of the technical capacity will be available during 10:00 10.09.2026. – 14:00 10.09.2026. Drávaszerdahely (HU>CR) (GEDRAVAS1HHN) Elementary Point.
The Gas Connect Austria makes maintenance work on its own system from 6:00 on 11.06.2026. to 12:00 on 19.06.2026. 0% of the technical capacity will be available on the Austrian side of HAG.
The GASTRANS d.o.o. Novi Sad makes maintenance work on its own system from 6:00 on 02.06.2026. to 6:00 on 07.06.2026. 0% of the technical capacity will be available at the Serbian side
Maintenance works will be carried out on the TurkStream pipeline from 6:00 on 02.06.2026. to 6:00 on 10.06.2026.
The actual sheets are available on our website: Planned Outages
Best Regards,
FGSZ Ltd., TSO