Update 3: Incident in the area of Mosonmagyaróvár

2020. 10. 23.

Dear Network Users!

 

As you are aware, we discovered damages, qualified as an incident, on the high-pressure transmission system of FGSZ Ltd. in the vicinity of Lébény, Hungary. Due to the incident the technical capacity of the Mosonmagyaróvár interconnection point had to be reduced.

 

We hereby inform you that those network users who

  • had firm capacity booking for the concerned gas days at the Mosonmagyaróvár interconnection point during the time of the incident’s announcement, and
  • request new daily or within-day capacity booking at any other entry points (be it interconnection, storage, or production) during the time of the ongoing incident,

are entitled to a discount of 100% of the daily or within-daily capacity booking fee, up to the extent of the Mosonmagyarovár interconnection point’s technical capacity reduction affecting the portfolio of the given network user, expressed in kWh/hour/day.

 

We call the attention of our Network Users that this measure is a decision of FGSZ Ltd. concerning exclusively this incident, hence does not provide a point of reference for any other cases.

FGSZ Ltd

Subscribe Newsletter